← NewsAll
Darlington nuclear refurbishment finished early and under budget, but maintenance costs remain
Summary
Ontario says the fourth Darlington reactor returned to service four months early and the overall refurbishment came in $150 million below its $12.8-billion budget. OPG has reported additional maintenance needs at Darlington, with identified items totalling roughly $2.65 billion.
Content
Construction on the fourth and final refurbished reactor at Darlington Nuclear Generating Station concluded on Jan. 19, and initial power testing of Unit 4 is scheduled to begin later this month. The province announced the full refurbishment program cost $150 million less than the original $12.8-billion budget and is intended to extend the station's service to at least 2055. Ontario officials have cited the project’s on-time, on-budget outcome as evidence of Ontario Power Generation’s improved performance. At the same time, OPG has reported several additional maintenance needs that will require further spending.
Key details:
- Unit 4 construction officially ended Jan. 19, and initial power testing is scheduled later this month.
- The overall refurbishment program is reported as $150 million under the $12.8-billion budget and is meant to extend Darlington’s life for decades.
- OPG identified turbine rotor replacements at Darlington with an estimated cost of about $2 billion.
- Additional emergent work listed by OPG includes generator stator rewinds (~$300 million), primary moisture separator replacements (~$235 million), and a Unit 2 turbine control and auxiliary upgrade (~$115 million).
- Darlington was built in the 1980s–90s, has supplied roughly one-fifth of Ontario’s power historically, and its refurbishment program began in October 2016.
Summary:
The refurbishment project has delivered earlier completion for Unit 4 and a final cost modestly below the original budget, which provincial officials have cited as evidence of stronger project delivery. Identified follow-on maintenance at Darlington introduces additional costs and OPG has scheduled initial power testing for Unit 4 as the next step; further timing for the identified maintenance work is not specified.
